Romulus, Michigan

North Terminal Pedestrian Bridge

Construction of 180 foot pedestrian bridge connecting two existing buildings.

Ruby+Associates provided connection design for Prospect Steel and erection procedure assistance to Midwest Steel during construction of the 180 foot pedestrian bridge connecting the North Terminal to the Ground Transportation Center. The bridge connects two existing buildings, and crosses over an elevated roadway that remained open to traffic, making tolerances and clearances tight as three 35-45 ton bridge sections were placed.